BAS controls submittal checklist

By Bassirou Thiam, building automation engineer · Updated

A BAS controls submittal is the package the controls contractor sends for approval before construction: control schematics, wiring diagrams, network riser, points list per controller, written sequences of operation, valve and damper schedules, product data and BACnet PICS. After installation, the same drawings come back as record (as-built) documents.

What goes in the submittal?

Every spec has its own list, but they share a core. This checklist follows a typical Division 23 09 00 guide specification; tick each item against your own spec before sending.

ItemWhat reviewers look for
Control schematicsFlow diagrams showing fans, pumps, coils, dampers, valves and control devices
Wiring diagramsPower, signal and control wiring, point to point from field device to panel, with numbered terminals
Panel detailsControl panel faces: sizes, instruments and labeling
Damper and valve schedulesSizes, leakage and flow characteristics; actuator sizing if dampers are by others
Sequence of operationsA written description, referring to the system point names
Network riser diagramWiring types, protocols, floor penetrations, panels labeled with address and device instance, all routers and switches
Points listPer system controller: inputs and outputs, point numbers, controlled device, device location
Motor control detailsStarter and VFD wiring for every automatically controlled motor
Floor plansLocations of control panels, thermostats and devices in occupied space
Product dataManufacturer literature for each device, with settings and ranges
BACnet PICSProtocol Implementation Conformance Statement for each DDC controller
Front-end softwareDescription and revision level of the operator workstation software
Variance letterEvery item that differs from the spec or the sequences

What comes after approval?

  • Sample graphics. Many specs ask for typical operator graphics before programming starts.
  • Checkout and commissioning forms. Blank test reports per panel or system, filled in at startup.
  • Record documents. At closeout, as-built versions of the shop drawings and product data, test reports and trend logs, and the O&M manual.

Why do submittals get rejected?

  • an item of the spec list is missing (the PICS and the variance letter are often forgotten);
  • the riser, the points list and the sequences disagree on a point name or a controller;
  • addresses or device instances are duplicated or missing on the riser;
  • the drawings describe a generic system instead of this job.

Most of these come from retyping the same information in several documents. Keeping the riser and the points list in one source is the simplest fix: see how to make a riser and what goes in a points list.

Sources

  1. Siemens, guide specification Section 23 09 00 – Building Automation System (submittals, network, point naming)
  2. WBDG, UFGS 23 09 00 – Instrumentation and Control for HVAC (U.S. Department of Defense)
  3. UConn, Appendix V – Building Automation Standards
  4. BACnet Testing Laboratories (BTL), product listings

Related

Free trial

Your next submittal, consistent from day one.

Start with one of your current jobs. Change a device and watch the riser and the points list follow.

7 days free · cancel in one click

Bassirou Thiam · founder of Structio