Should BAS design start before the equipment is approved?

By Bassirou Thiam, building automation engineer · Updated

Ideally not. Designing controls around equipment that is still “or equal”, with a sequence under revision, usually means designing twice. In practice, equipment is often only fixed after buyout, so start with what is firm and list clearly what each drawing assumes.

What to have before starting

  • the selected equipment model, not “or equal”;
  • its electrical requirements and the controls points it exposes;
  • the communication protocol;
  • the sequence of operations, accepted;
  • the sensor locations;
  • the alarms the owner expects.

When you have to start anyway

Mark provisional items on the drawings and keep the riser and points list in one source, so the second pass is an update, not a redraw.

Sources

  1. Field discussion, r/MEPEngineering: “Approved equipment data before controls design”

Related

Free trial

Your next submittal, consistent from day one.

Start with one of your current jobs. Change a device and watch the riser and the points list follow.

7 days free · cancel in one click

Bassirou Thiam · founder of Structio